Which statement is true about cost avoidance savings identified at pre-programming?

Study for the Certified Defense Financial Manager (CDFM) Exam 1. Engage with flashcards and multiple choice questions, with hints and explanations for each query. Prepare confidently for your exam!

Multiple Choice

Which statement is true about cost avoidance savings identified at pre-programming?

Explanation:
Cost avoidance savings identified at pre-programming reflect the potential to cut costs across the entire life cycle of a program. At this stage, analysts look at how a decision will impact all future costs—from development and procurement through operations, maintenance, and eventual disposal. Since avoidance means not incurring costs in the future, the savings are not limited to just initial setup, ongoing operations, or maintenance alone; they apply to the total lifecycle. Therefore, the best description is that pre-programming cost avoidance covers the entire life-cycle of program costs.

Cost avoidance savings identified at pre-programming reflect the potential to cut costs across the entire life cycle of a program. At this stage, analysts look at how a decision will impact all future costs—from development and procurement through operations, maintenance, and eventual disposal. Since avoidance means not incurring costs in the future, the savings are not limited to just initial setup, ongoing operations, or maintenance alone; they apply to the total lifecycle. Therefore, the best description is that pre-programming cost avoidance covers the entire life-cycle of program costs.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy