Which two variances are typically assessed in Earned Value Management?

Study for the Certified Defense Financial Manager (CDFM) Exam 1. Engage with flashcards and multiple choice questions, with hints and explanations for each query. Prepare confidently for your exam!

Multiple Choice

Which two variances are typically assessed in Earned Value Management?

Explanation:
In Earned Value Management, the focus is on measuring performance against the plan in terms of schedule and cost. The two variances used for this are Schedule Variance and Cost Variance. Schedule Variance (SV) is EV minus PV, showing whether the earned value of work is ahead of or behind the planned value. A positive SV means you’re ahead of schedule on earned value; a negative SV means you’re behind. Cost Variance (CV) is EV minus AC, indicating whether the value of work completed costs more or less than what was actually spent. A positive CV means you’re under budget (cost efficiency), while a negative CV signals a cost overrun. Quality variance isn’t part of EVM’s standard variances, since EVM concentrates on cost and schedule performance (with CPI and SPI as related efficiency measures). So the two variances typically assessed are schedule variance and cost variance.

In Earned Value Management, the focus is on measuring performance against the plan in terms of schedule and cost. The two variances used for this are Schedule Variance and Cost Variance. Schedule Variance (SV) is EV minus PV, showing whether the earned value of work is ahead of or behind the planned value. A positive SV means you’re ahead of schedule on earned value; a negative SV means you’re behind. Cost Variance (CV) is EV minus AC, indicating whether the value of work completed costs more or less than what was actually spent. A positive CV means you’re under budget (cost efficiency), while a negative CV signals a cost overrun.

Quality variance isn’t part of EVM’s standard variances, since EVM concentrates on cost and schedule performance (with CPI and SPI as related efficiency measures). So the two variances typically assessed are schedule variance and cost variance.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy